Rožna ulica 15, Idrija
Rožna ulica 15
5280
Idrija, Slovenia
architetto
Owner
User
Contact Details
Other Information
Climate Zone DFc
Altitude 330 s.l.m.
HDD 250
Conservation Area:
Si
Level of Protection:
heritage of local importance
Year of last renovation:
2018
Year of previous renovation:
0
Secondary use:
Offices
Building occupancy:
Permanently occupied
Building typology:
Semidetached house
Number of floors:
4
Basement yes/no:
No
Number of heated floors:
4
Gross floor area [m²]:
1108,61
Volume [m³]:
3056,21
NFA calculation method:
External finish:
Rendered
Internal finish:
Plastered (on hard)
Roof type:
Pitched roof
RENOVATION PROCESS
Architecture
BUILDING DESCRIPTION
State of repair
HERITAGE SIGNIFICANCE
Aim of retrofit
Idrija Municipality
Mestni trg 1, 5280 Idrija
Studio M
Bazoviška ulica 5, Tolmin
National Institute for the Protection of Cultural Heritage in Slovenia
Delpinova ulica 16, 5000 Nova Gorica
RETROFIT SOLUTIONS
External Walls
stone masonry wall
The outside walls were statically reinforced. For the needs of energy rehabilitation, a 15 cm layer of thermal insulation was added on the outside. Facade ornaments were made anew.
30 mm
500 mm
30 mm
3mm
150 mm
500 mm
12 mm
12 mm
Windows
Facade windows
Window replicas were made specially for the building according to the conservation plan.
Existing window type | Box-type window |
Existing glazing type | Single |
Existing shading type | NA |
New window type | Casement window |
New glazing type | Double |
New shading type | NA |
Other interventions
ROOF
GROUND FLOOR
13 mm
100 mm
20 mm
20 mm
220 mm
1 mm
12 mm
10 mm
50 mm
100 mm
10 mm
60 mm
120 mm
10 mm
100 mm
HVAC
HEATING
DOMESTIC HOT WATER
The building is connected to the gas grid of the town.
New primary heating system | |
---|---|
New system type | Boiler |
Fuel | Gas |
Distribuition system | Radiators |
Nominal power | 45 kW kW |
Common gas boiler is being used both for heating and preparation of domestic hot water. There was no influence on protected elements.
New DHW system | |
---|---|
Type | with heating system |
Hot_water_tank | Si |
With heat recovery | No |
Energy Efficiency
Voluntary certificates: No
Primary Energy 97 kWh/m2.y
Consumption_estimation_After: 44 kWh/m2.y
Primary Energy
Consumption_estimation_Calculation_method: Steady state simulation (e.g. EPC, PHPP)
Consumption_estimation_After: 97 kWh/m2.y
Costs
The building was damaged in the eartquake and included in the national programme of refurbishment that was managed by the technical office. The overall budget is a combination of national and local public funding (Municipality of Idrija).
683.000 EUR (total)
No